Located on the prominent corner of Palace Court and Moscow Road, moments from Kensington Gardens, the Esca House project involved a complex demolition programme within a highly sensitive and constrained central London environment.
 
The works incorporated a carefully engineered top-down demolition methodology, alongside the retention and protection of the existing façade. A key challenge was the installation of protective scaffolding over a live London Underground line, ensuring the continued protection of the railway infrastructure throughout the demolition works.
 
Delivered in close proximity to neighbouring properties, the project required careful planning, coordination and regular communication with local residents and stakeholders. Close liaison with London Underground (LUL) and Westminster City Council was also essential to ensure the works were carried out safely and in accordance with the relevant requirements.
 
The project demonstrates Demoforce's expertise in delivering technically challenging demolition and enabling works, particularly where structural retention, live infrastructure and sensitive neighbouring environments demand a high level of technical and operational control.

Location: Bayswater, London
Client: Fancourt Property Group
Scope of Works
  • Asbestos Removal and Soft Strip
  • Top-down demolition
  • Top-down demolition
  • Enabling works
  • Scaffold façade retention scheme
  • Installation of 70 tonnes of kentledge blocks
  • Top-down demolition of a two-storey structure
  • Piling works
  • Façade Retention
  • Party Wall Works
  • Working on live London Underground Line
  • Working over live London Underground Line
  • Concrete cutting